December 2006 Photos
The Learning Resources Center construction project was completed in December. Library staff has been busy moving the contents of the Lesher Library into this new facility. Thanks to Parsons Brinckerhoff, the LRC project was completed ahead of schedule and on budget. The old Lesher Library will be taken off-line and prepared for remodeling into a one-stop student services building.
Book stacks on the second floor
Installation of landscaping in front of the building
Student study area
November 2006 Photos
Construction progress is on schedule with exterior concrete being poured, as well as finishing work on the interior. This includes carpet installation, finishing millwork, and installation of the bookshelves. The project should be complete and ready to turn over to the College by mid-December.
Second floor book stacks
Lobby area
Lounge
October 2006 Photos
These photos show work on the concrete walkways being poured in front of the Learning Resources Center, as well as view inside the main floor area. Some of the continuing activities this month include carpet installation on the first floor, installation of ceiling tiles, installation of bathroom fixtures, and the routing of the phone lines. Progress in on-schedule for this impressive facility.
Entryway Concrete WorkMain open area of building
Stairway
September 2006 Photos
As the interior areas of the Learning Resources Center continue to take shape, work on the exterior areas of the building will begin. These projects include installation of the sprinkler system and other landscaping work including the pouring of cement for sidewalks. Glass is also being installed this month.
Installation of sprinkler system
Glass will be installed in the LRC building
Installation of sprinkler system
August 2006 Photos
Progress remains on schedule for what will be the largest educational building on campus, the Learning Resources Center . This 67,000 square-foot facility will boast a state-of-the-art data network system, high capacity internet connections, and will serve as the space to house the library's 50,000 book collection.
These photos show the present state of the interior of the facility and one shot of the continuing exterior stucco work.
Exterior stucco work
LRC interior
LRC interior
June 2006 Photos
The Learning Resources Center continues to make great progress toward completion. This month's scheduled activities include completion of texturing of the exterior walls, as well as completion of the roof. Work will continue on the ductwork and electrical systems.
- Content 1
- Content 2
- Content 3
May 2006 Photos
The new Learning Resources Center project is continuing to take shape. This month construction crews completed the exterior sheathing, began putting on the first exterior stucco coat, and continued to work on various ductwork and electrical projects.
Exterior of LRC project
Exterior of LRC project
Exterior of LRC project
April 2006 Photos
North view of the Learning Resources Center showing the exterior "skin" of the building
Close-up of the facility looking west
Water on the first floor from an unusual rainy month of March. Progress continues on the exterior walls, seen here from the interior.
March 2006 Photos
First Floor Looking North - This is the first floor of the Learning Resources Center looking north through the building.
First Floor Study Rooms - The study rooms on the First Floor are taking shape.
LRC South Elevation -This is the Learning Resources Center as seen from south. This parking lot is at the back of the Vocational Building.
February 2006 Photos
A student walks by the sourthern side of LRC, which will be the facility’s main entrance.
The interior of the LRC from another angle, showing the ductwork for the heating and air conditioning system.
The heating and air conditioning system for the Learning Resources Center is ready to be installed.